Citrus Solar Energy Center

operating solar center

Founded
2016
Evidence class
publicly verified operating
Place
DeSoto County
District
Peace River valley
Status as of 12 September 2026
Operating; in service December 2016 per the plan's existing facilities schedule.
Connections
2 edges, 2 distinct neighbours · betweenness 0.000 (rank 163 of 243) · location and lineage only 0.000 (rank 129) · outside share 0.50
Confidence
High · sources: [TYSP] (register)

The first of the 74.5 megawatt generation in DeSoto County, seven years after the pilot plant at Arcadia [TYSP].